Edmonds School District #15
 

 

Timeline: Capital Improvements Across the District

New Lynnwood High School Update

Did you know? Money from the 2006 Capital Construction Bond and from the sale or ground lease of district property legally must go toward capital improvements. It cannot help fund instruction or staffing needs.

*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

Elementary and K-8 Schools

Beverly ElementaryView the timeline of the projects (PDF)
Location: 5221 168th Street SW, Lynnwood

Funding Source

Project Description

Est. Completion Date*

2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Replace HVAC system
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2008

    2006 Capital Construction Bond

  • Replace moveable partition for stage
  • 2009

    2006 Capital Construction Bond

  • Replace gym floor
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • Fall-Winter 2009

    2004 Capital Levy

  • Capital Partnership Program: playground feature
  • 2004 Capital Levy

  • Field improvements: backstop upgrade
  • 2004 Capital Levy

  • Field improvements: drainage, irrigation, and turf renovation
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Brier ElementaryView the timeline of the projects (PDF)
    Location: 3625 232nd Street SW, Brier

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2006 Capital Construction Bond

  • Revise traffic and parking
  • 2009

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Capital Partnership Program: track
  • 2004 Capital Levy

  • Field improvements: fencing
  • 2004 Capital Levy

  • Field improvements: drainage, irrigation, and turf renovation
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Cedar Valley Community SchoolView the timeline of the projects (PDF)
    Location: 19200 56th Avenue W, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Field improvements: backstop upgrade
  • 2004 Capital Levy

  • Capital Partnership Program: fastpitch field
    **Project revised to be at Edmonds-Woodway High
  • Project revised

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Cedar Way ElementaryView the timeline of the projects (PDF)
    Location: 22222 39th Avenue W, Mountlake Terrace

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Field improvements: backstop upgrade
  • 2004 Capital Levy

  • Field improvements: fencing
  • 2004 Capital Levy

  • Field improvements: drainage, irrigation, and turf renovation
  • In progress

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Chase Lake Community SchoolView the timeline of the projects (PDF)
    Location: 21603 84th Avenue W, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    College Place ElementaryView the timeline of the projects (PDF)
    Location: 20401 76th Avenue W, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Replace playground paving
  • 2009

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Field improvements: fencing
  • 2004 Capital Levy

  • Field improvements: drainage, irrigation, and turf renovation
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Edmonds ElementaryView the timeline of the projects (PDF)
    Location: 1215 Olympic Avenue, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Replace domestic water piping
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2006 Capital Construction Bond

  • Provide vestibule for office
  • 2009

    2006 Capital Construction Bond

  • Replace gym floor
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Field improvements: fencing
  • 2004 Capital Levy

  • Capital Partnership Program: playground
  • 2004 Capital Levy

  • Capital Partnership Program: field renovation
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Evergreen ElementaryView the timeline of the projects (PDF)
    Location: 6004 237th Street SW, Mountlake Terrace

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2006 Capital Construction Bond

  • Improve acoustics in one classroom unit
  • 2009

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Capital Partnership Program: playground feature
  • 2004 Capital Levy

  • Field improvements: asphalt, backstop upgrade, and fencing
  • 2004 Capital Levy

  • Field improvements: drainage, irrigation, and turf renovation
  • In progress

    2004 Capital Levy

  • Earthquake safety upgrades
  • Fall-Winter 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Hazelwood ElementaryView the timeline of the projects (PDF)
    Location: 3300 204th Street SW, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Resolve off-site drainage
  • 2009

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade data cabling
  • 2004 Capital Levy

  • Capital Partnership Program: stairs and outdoor instructional seating
    Updated: Project Canceled
  • Project Canceled

    2004 Capital Levy

  • Field improvements: fencing
  • 2004 Capital Levy

  • Field improvements: backstop upgrade and drainage, irrigation, and turf renovations
  • 2004 Capital Levy

  • Earthquake safety upgrades
  • 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Hilltop ElementaryView the timeline of the projects (PDF)
    Location: 20425 Damson Road, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Field improvements: backstop upgrade
  • 2004 Capital Levy

  • Field improvements: drainage, irrigation, and turf renovations
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Lynndale ElementaryView the timeline of the projects (PDF)
    Location: 7200 191st Place SW, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    Revenue from Surplus Property

  • Build new school facility
  • 2013

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2008

    2006 Capital Construction Bond

  • Replace gym floor
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Capital Partnership Program: reader board
  • 2004 Capital Levy

  • Field improvements: asphalt
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Lynnwood ElementaryView the timeline of the projects (PDF)
    Location: 18638 44th Avenue W, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2006 Capital Construction Bond

  • Replace multi-purpose room platform steps
  • 2006 Capital Construction Bond

  • Revise traffic and parking
  • 2006 Capital Construction Bond

  • Improve acoustics in multi-purpose room
  • 2009

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Capital Partnership Program: fencing and reader board
  • 2004 Capital Levy

  • Field improvements: backstop upgrade
  • 2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Field improvements: asphalt
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Madrona School View the timeline of the projects (PDF)
    Location: 9300 236th Street SW, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    Revenue from Surplus Property

  • Build new school facility
  • 2012

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Field improvements: backstop upgrade
  • 2008-09

    2004 Capital Levy

  • Capital Partnership Program: emergency structure
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Maplewood Parent Co-Op View the timeline of the projects (PDF)
    Location: 8500 200th Street SW, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Martha Lake Elementary View the timeline of the projects (PDF)
    Location: 17500 Larch Way, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Meadowdale Elementary View the timeline of the projects (PDF)
    Location: 6505 168th Street SW, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Capital Partnership Program: playground feature
  • 2004 Capital Levy

  • Field improvements: fencing
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Mountlake Terrace Elementary View the timeline of the projects (PDF)
    Location: 22001 52nd Avenue W, Mountlake Terrace

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2008

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • Summer 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Oak Heights Elementary View the timeline of the projects (PDF)
    Location: 15500 18th Avenue W, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2008

    2006 Capital Construction Bond

  • Upgrade covered play structure
  • 2009

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Capital Partnership Program: playground feature
  • 2004 Capital Levy

  • Field improvements: backstop upgrade and drainage, irrigation, and turf renovation
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Seaview Elementary View the timeline of the projects (PDF)
    Location: 8426 188th Street SW, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Sherwood Elementary View the timeline of the projects (PDF)
    Location: 22901 106th Avenue W, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Spruce Elementary View the timeline of the projects (PDF)
    Location: 17405 Spruce Way, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2008

    2006 Capital Construction Bond

  • Replace HVAC system
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Field improvements: backstop upgrade
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Terrace Park School View the timeline of the projects (PDF)
    Location: 5409 228th Street SW, Mountlake Terrace

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Westgate Elementary View the timeline of the projects (PDF)
    Location: 9601 220th Street SW, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2008

    2006 Capital Construction Bond

  • Replace gym flooring
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Field improvements: asphalt and fencing
  • 2004 Capital Levy

  • Field improvements: drainage, irrigation, and turf renovation
  • In progress

    2004 Capital Levy

  • Earthquake safety upgrades
  • Summer-Fall 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Woodway Elementary View the timeline of the projects (PDF)
    Location: 9521 240th Street SW, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2008

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Field improvements: backstop upgrade
  • 2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Field improvements: asphalt
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

     

    Middle Schools

    Alderwood Middle SchoolView the timeline of the projects (PDF)
    Location: 20000 28th Avenue W., Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    Revenue from Surplus Property

  • Build new school facility
  • Fall 2013

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade science lab safety
  • 2004 Capital Levy

  • Athletic fields: Add under-irrigation to football/soccer and baseball fields and irrigation to fastpitch field
  • 2009

    2004 Capital Levy

  • Install asphalt and all-weather surface to runway and high-jump areas
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Brier Terrace Middle SchoolView the timeline of the projects (PDF)
    Location: 22200 Brier Road, Brier

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade heating/ventilation controls
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2006 Capital Construction Bond

  • Replace moveable partitions in two classrooms
  • 2009-10

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade science lab safety
  • 2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Athletic fields: Add under-drainage and irrigation to football/soccer and baseball fields and irrigation to fastpitch field
  • 2009

    2004 Capital Levy

  • Install asphalt and all-weather surface to runway and high-jump areas
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    College Place Middle SchoolView the timeline of the projects (PDF)
    Location: 7501 208th Street SW, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade science lab safety
  • 2004 Capital Levy

  • Earthquake safety upgrades
  • 2004 Capital Levy

  • Athletic fields: Add under-drainage and irrigation to football/soccer and baseball fields and irrigation to fastpitch field
  • 2009

    2004 Capital Levy

  • Install asphalt and all-weather surface to runway and high-jump areas
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Meadowdale Middle School View the timeline of the projects (PDF)
    Location: 6500 168th Street SW, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Build new school facility
  • Fall 2011

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade science lab safety
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

     

    High Schools

    Edmonds-Woodway High SchoolView the timeline of the projects (PDF)
    Location: 7600 212th Street SW, Edmonds

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade science lab safety
  • 2004 Capital Levy

  • Install FieldTurf and lighting to fastpitch field
  • 2004 Capital Levy

  • Under-drain baseball field
  • 2008-09

    2004 Capital Levy

  • Build retaining wall with safety fence and add fill to extend south practice field
  • 2009-10

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Lynnwood High School View the timeline of the projects (PDF)
    Location: 3001 184th Street SW, Lynnwood (current) -- 18217 North Road, Bothell (future)

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Build new school facility
  • Fall 2009

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Design new facility
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Resurface and paint track (partially funded by the City of Lynnwood)
  • 2004 Capital Levy

  • Upgrade science lab safety
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Meadowdale High School View the timeline of the projects (PDF)
    Location: 6002 168th Street SW, Lynnwood

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Eradicate Scotch broom
  • 2006 Capital Construction Bond

  • Install one new fume hood
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade science lab safety
  • 2004 Capital Levy

  • Install all-weather track
  • 2004 Capital Levy

  • Capital Partnership Program: field renovations
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Mountlake Terrace High School View the timeline of the projects (PDF)
    Location: 21801 44th Avenue W, Mountlake Terrace

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Install two new fume hoods
  • 2006 Capital Construction Bond

  • Replace stage flooring
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade data cabling
  • 2004 Capital Levy

  • Upgrade science lab safety
  • 2004 Capital Levy

  • Install FieldTurf to field and lights to tennis courts
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Scriber Lake High/Options Program (Alternative Learning Center) View the timeline of the projects (PDF)
    Location: 20525 52nd Avenue W, Lynnwood (current) -- 20420 68th Avenue W, Lynnwood (future)

    Funding Source

    Project Description

    Est. Completion Date*

    Revenue from Surplus Property

  • Renovate existing ESC facility for classroom purposes
  • Fall 2009

    2004 Capital Levy

  • Design new facility
  • 2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

     

    Other Programs

    Alderwood Early Childhood CenterView the timeline of the projects (PDF)
    Location: 2000 200th Place SW, Lynnwood (former Alderwood Elementary)

    Funding Source

    Project Description

    Est. Completion Date *

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2004 Capital Levy

  • Technology: Install schoolwide technology tools
  • 2004 Capital Levy

  • Field improvements: backstop upgrade
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.

    Edmonds Homeschool Resource CenterView the timeline of the projects (PDF)
    Location: 23200 100th Avenue W, Edmonds (former Woodway High School)

    Funding Source

    Project Description

    Est. Completion Date*

    2006 Capital Construction Bond

  • Install emergency storage structure
  • 2006 Capital Construction Bond

  • Upgrade data cabling
  • 2009

    2004 Capital Levy

  • Technology: Install a projector, document presenter, and instructional laptop in each classroom
  • 2004 Capital Levy

  • Technology: Install mobile lab equipment
  • 2004 Capital Levy

  • Technology: Install additional computers in classrooms
  • Fall 2006-Spring 2009

    2004 Capital Levy

  • Upgrade science lab safety
  • *Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.


    Edmonds School District - 20420 68th Ave. W. Lynnwood, Washington 98036-7400
    Phone: (425) 431-7000 — FAX: (425) 431-7006

    Updating our Website: Voter-approved 2008 Technology Levy dollars will be used to improve our site.
    This site best viewed with Internet Explorer 6.0+ or Firefox 2.0+.
    Questions about our website, click here.
    General questions should be directed to Community Relations.
    To view our nondiscrimination policy, click here.